Checklist as PDF
Chapters
Transcript
From decision to site
A complex by the sea, many owners. Rust on the concrete, water in the flats, old pipes. Sooner or later, every owners' association has to carry out repairs. How does it work – from the first resolution to the start of the works?
The order
A fixed order works best: first understand, then plan, then award the contract on comparable bids – and then start the works properly. Twelve steps. And three times, the general meeting decides.
Gate 1: commission the survey
It starts with a resolution: the association has the situation investigated – with a budget for it. That is the first gate. If there is an acute danger, the administrator arranges for it to be made safe at once and reports on it.
Survey and diagnosis
A qualified professional surveys the building: every damaged element gets a number, a photo and a place on the drawings. Measurements on site and in the laboratory show how deep carbon dioxide has penetrated, how much salt is in the concrete, how thick the cover over the steel is and how strong the concrete still is. Because the cause determines the repair.
Asbestos
Older buildings often contain asbestos cement – in sheets, pipes or cladding. The rule is: before work starts, it must be established whether asbestos is involved, and the result belongs in the health and safety study of the design. It is wise to clarify it with samples before the design stage – then it is planned for, not discovered on site.
Concept
From the findings comes a concept with priorities: safety first, then protection against moisture, then durability. With options and a cost estimate – so that the general meeting knows what it is deciding on.
Gate 2: concept and appointments
Second gate: the general meeting approves the concept and priorities – and the appointments for the design, the site direction and the health and safety coordination, with their fees. So from the outset it is clear what design and supervision will cost. If it wishes, the association can also appoint project management – in Spanish gestión y control de proyecto: not required, but on large projects a great help. It keeps deadlines, costs and design documents together and keeps all owners informed. Project management is not site direction and does not replace it.
The design: who draws it up
Then the design is drawn up. In the Canary Islands, anyone altering structural elements needs a design – for mere conservation and maintenance work, none is needed. It can be drawn up by an architect – and, for repairs that do not substantially alter the building, also by a technical architect. If the structural system of a residential building as a whole is substantially altered, the designer and the director de obra must be an architect.
Bill of quantities and permit
The heart of the design is the bill of quantities: every item with quantity and quality. That turns every decision of the general meeting into an item that can be checked. Depending on the type of work, the association then needs a permit from the town hall or submits a prior notification – a comunicación previa.
Comparable bids
Now the contractors are invited. A private association is not legally required to issue an invitation to tender. But good practice is: several contractors bid on the same bill of quantities. A tender comparison shows all owners, item by item, where the differences lie – in their own language.
Gate 3: contractor, budget, contract
Third gate: the general meeting chooses the contractor and approves the total budget – works, fees, charges and a contingency – together with the special levy and the payment schedule. The contract sets out price, deadlines, warranties and rain protection. Payment is made for what has been measured and certified by the site direction.
Formal start of works
Before the first hammer blow, everything is in writing: who forms the site direction – the dirección facultativa – and, as soon as several companies or self-employed workers are on site, who coordinates health and safety; the approved health and safety plan; the workplace opening notice to the labour authority; and, if asbestos is involved, an approved work plan from a registered specialist firm. Site direction is taken on by qualified professionals appointed by the association – each role stays separate. Then the site start record is signed.
Information and works
All owners are told the schedule, the contacts and the rain protection – including those who do not live on site. Protect first, then open up. And during the works: anything beyond the approved budget goes to the general meeting before it is commissioned. Only urgent matters are arranged at once by the administrator – who then reports on them. Every owner can inspect the association's documents.
10 questions for your association
Ten questions any association can use to check where it stands. One: Is there a written diagnosis with measured values? Two: Was asbestos checked with samples? Three: Is there a signed design by a qualified professional? Four: Does everything the general meeting approved appear in the bill of quantities? Five: Did all contractors bid on the same basis? Six: Did the general meeting approve the total budget with all costs, and the levy? Seven: Were owners told in writing, before work started, who forms the site direction and who coordinates health and safety? Eight: Before work started, were the approved health and safety plan, the permit or prior notification and, if asbestos is involved, the work plan in place? Nine: Is payment made only against certificates from the site direction – and are extra costs approved in advance? Ten: Does everyone know the schedule, the contacts and the rain protection – and can they inspect the documents? For small maintenance jobs, not every point is required. The bigger the work, the more each yes matters. And every no is a question, not an accusation: ask in writing for the missing document.
To sum up
Repair is teamwork: the general meeting, the administrator, the professionals and the contractor. When the order is right, the repair lasts. Know first, then build.
Sources and standards
- LPH – Ley 49/1960 (Arts. 10, 14 c, 20)
- LOE – Ley 38/1999 (Arts. 2, 10–13)
- Ley 12/1986 (Art. 2)
- RD 1627/1997 (Arts. 3, 7, 19)
- RD 847/2026 (Arts. 10–13, 18)
- CTE – RD 314/2006 (Part I, Annex I)
- Decreto 182/2018, Canary Islands (Art. 7)
- Ley 4/2017, Canary Islands (Arts. 330, 332)
- UNE-EN 1504-9:2011